Department of Real Estate Services: Department of Corrections Projects
DC Home Mayor Fenty DC Guide Residents Business Visitors DC Government Kids

Department of Real Estate Services

OPM HOME
DRES HOME
ABOUT OPM
SERVICES
SERVICES
INFORMATION
INFORMATION
BUSINESS PORTAL
ONLINE SERVICE
  REQUESTS

TOOLS & RESOURCES
ONLINE SERVICE
  REQUESTS

About DRES
Director's Biography
DRES Organizational
 Chart

How to Reach Us
Ask the Director
FOIA Requests
News Room
Employment
 Opportunities

Site Map
Performance
Construction Division
Facilities Division
Portfolio Division
Protective Services
 Division

Contracting & Procurement
Energy Management
Publications
Eastern Market
Consolidated Forensic
 Laboratory

College Internship
 Program

Energy Conservation
 Campaign

Government Center
 Projects

Green Buildings
Green Roofs
DRES Performance
 Management

Permanent Supportive
 Housing Program

Southwest Waterfront
Case Studies
Director's Biography
OPM Organizational
Chart

Employment
   Opportunities

How to Reach Us
What We Do
Business Opportunities
Solicitations for Space
Standard Forms
District Facilities Plan
LEED Certification
 Guidebook

Project Delivery Manual
Workplace Design
 Guidelines

DC Properties
How to Research
 Property

Department of Corrections Projects
 
DC Department of Corrections
 
Project Overview
This project includes the renovation of numerous aspects of the District’s jails. They range from mechanical and electrical upgrades, security and life safety upgrades, to reconfigurations and expansions.
 
_________________________________________________
 
 
Project: Renovate Cell Doors & Motors
 
Description
This project will replace approximately 1,600 cell door mechanisms in eighteen (18) cellblocks and includes the replacement of all controls and wiring.
 
Schedule
Milestone Completion Date
Design Summer 2009 - Winter 2009
Construction Spring 2010 - Winter 2011
Project Completion Winter 2011
 
Budget
$14.5 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Upgrade Fire Alarm and Sprinkler System
 
Description
This project includes the installation of new heat, fire, and smoke detectors, panels, standpipes, sprinkler heads, and other fire prevention system upgrades.
 
Schedule
Milestone Completion Date
Design Fall 2006 - Summer 2007Complete
Construction Winter 2008 - Winter 2009
Project Completion Winter 2009
 
Budget
$6.1 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Upgrade Central Security System
 
Description
This project includes camera surveillance, alarm, motion detectors, perimeter fencing, lighting & inmate RFID systems.
 
Schedule
Milestone Completion Date
Design Spring 2008 - Winter 2009
Construction Spring 2010 - Summer 2011
Project Completion Summer 2011
 
Budget
$3.8 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: General Renovation of Sallyport at DC Jail
 
Description
This project includes camera surveillance, alarm, motion detectors, perimeter fencing, lighting & inmate RFID systems.
 
Schedule
Milestone Completion Date
Design Summer 2009 - Summer 2010
Construction Fall 2010 - Winter 2011
Project Completion Winter 2011
 
Budget
$5.5 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Inmate Processing Center
 
Description
This project includes camera surveillance, alarm, motion detectors, perimeter fencing, lighting & inmate RFID systems.
 
Schedule
Milestone Completion Date
Design Fall 2009 - Summer 2010
Construction Fall 2010 - Winter 2011
Project Completion Winter 2011
 
Budget
$9 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Renovations at Central Detention Facility- Exterior Structural Renovations
 
Description
This project will seal all exterior structural elements of the building, including pre-cast panels and some windows. 
 
Schedule
Milestone Completion Date
Design Fall 2009
Construction Winter 2009 - Summer 2010
Project Completion Summer 2010
 
Budget
$1.2 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Renovate Inmate Showers at Central Detention Facility
 
Description
This project includes installing new shower stalls, piping, drains, lines, mop drains, floors, walls, ceilings, and other shower systems. 
 
Schedule
Milestone Completion Date
Design Summer 2009
Construction Summer 2009 - Summer 2010
Project Completion Summer 2010
 
Budget
$2.5 million
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Energy Power System at Central Detention Facility
 
Description
This project includes the installation of a 1,100 KW emergency generator and reconfiguration of the electrical system. 
 
Schedule
Milestone Completion Date
Design Fall 2005Complete
Construction Winter 2009
Project Completion Winter 2009
 
Budget
$800,000
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Renovate Visitors Entrance at Central Detention Facility
 
Description
This project includes the reconfiguration and expansion of the existing visitors entrance. 
 
Schedule
Milestone Completion Date
Design Spring 2009 - Summer 2010
Construction Fall 2010 - Winter 2011
Project Completion Winter 2011
 
Budget
$1 million 
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Steam Supply and Return
 
Description
This project includes the phased replacement of all supply traps, return lines, condensate tanks & pumps, traps, valves, strainers and joints. 
 
Schedule
Milestone Completion Date
Design Spring 2006 - Summer 2009
Construction Spring 2010 - Winter 2010
Project Completion Winter 2010
 
Budget
$800,000
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: Environmental Remediation
 
Description
This project will undertake remedial action for leaked underground storage tanks. 
 
Schedule
Milestone Completion Date
Design
Construction Fall 2010
Project Completion Fall 2010
 
Budget
$300,000
 
Project Manager
Satish Bagai 
 
_________________________________________________
 
 
Project: HVAC Replacement
 
Description
This project includes the replacement of the HVAC (Heating/Ventilation/Air Conditioning) system for the entire facility.  Original HVAC Completed. Chillers replacement in Design and added to the Project 
 
Schedule
Milestone Completion Date
Design Winter 2008Complete 
Construction Winter 2009 - Spring 2010
Project Completion Spring 2010
 
Budget
$9.3 million
 
_________________________________________________
 
 
Project: Roof Replacement at Central Detention Facility
 
Description
This project includes the replacement of approximately 78,000 square feet of roof over the Administration Building and the housing blocks at the jail. 
 
Schedule
Milestone Completion Date
Design Fall 2008 - Winter 2008Complete
Construction Summer 2009 - Summer 2009 Complete
Project Completion Winter 2009Complete
 
Budget
$2 million
 
_________________________________________________
 
 
Project: Floor Repair at Central Detention Facility
 
Description
This project includes floor repairs in various locations, including the North 1 and North 2 cellblocks. 
 
Schedule
Milestone Completion Date
Design Summer 2007 - Winter 2008Complete
Construction Winter 2008 - Fall 2008 Complete
Project Completion Fall 2008Complete
 
Budget
$200,000
 
_________________________________________________
 
 
Project: Parking Garage
 
Description
This project includes the pre-design of a 700 car parking garage. 
 
Schedule
Milestone Completion Date
Design Spring 2008 - Spring 2009Complete
Construction
Project Completion
 
Budget
$500,000