Americans with Disabilities Act Compliance
Project Overview The District is working towards compliance with the Americans with Disabilities Act (ADA) in all of its properties. This program encompasses ADA Compliance Surveys, ADA Compliance Design, Building Renovation, and Signage Construction.
_________________________________________________
Project: Emery Shelter
Description:
The Emery Shelter, a former school building, is a 2-story structure with a basement that was constructed in 1902. The current use for this facility is a transitional shelter for 100 men. The construction work in progress for this site will provide an accessible entrance, access to all levels of the building via elevator, accessible toilet rooms, door and hardware modifications and the installation of an accessible parking space, all in compliance with Americans with Disabilities Act (ADA) guidelines. The listed modifications will provide improved public access to this facility and its programs.
Schedule:
| Design |
Spring 2008 - Fall 2008 |
| Construction |
Early 2009 - Fall 2009 |
| Project Completion |
Fall - 2009 |
Budget
$947,000
_________________________________________________
Project: Madison Shelter
Description:
The Madison Shelter is a historic 2-story building plus basement, that was constructed in 1889. This former elementary school serves as a shelter site for 68 women. A new elevator with an accessible entrance, modified toilet rooms and a new handicapped parking space will be constructed in compliance with Americans with Disabilities Act (ADA) guidelines. The completed ADA work will permit those with disabilities, greater access to this site and improved access to the facility’s programs.
Schedule:
| Design |
Spring 2008 - Fall 2008 |
| Construction |
Summer 2009 - Winter 2009 |
| Project Completion |
Winter 2009 |
Budget
$691,000
_________________________________________________
Project: New York Avenue Shelter
Description:
The New York Avenue Shelter is undergoing modifications to meet accessibility requirements in compliance with Americans with Disabilities Act (ADA) guidelines. This facility provides Low Barrier Shelter for over 360 men, and Temporary Shelter for 12 men. Construction work underway for this site includes door/hardware modifications, toilet room modifications, installation of visual/audio fire alarm devices, ramps for floor level changes, handrail modifications, power door operators, signage and development of a handicapped parking space and ramp.
Schedule:
| Design |
Spring 2008 - Fall 2008 |
| Construction |
Early 2009 - Fall 2009 |
| Project Completion |
Fall 2009 |
Budget
$447,300
_________________________________________________
Project: Police Stations
Description:
This project includes upgrading the 4th District Police Department building in order to comply with ADA guidelines. The scope includes bathroom renovation, door hardware upgrade, signage installation,ramp accessibility upgrades, and accessible.
Schedule:
| Design |
Fall 2007 - Winter 2008 |
| Construction |
Winter 2008 - Summer 2009 |
| Project Completion |
Summer 2009  |
Budget
$536,000
_________________________________________________
Project: ADA Compliance Signage Construction
Description:
This project includes signage installation in eleven (11) buildings.
- 1700 Rhode Island Avenue, Youth & Family
- 5th District MPD
- 4th District MPD
- 2901 20th Street, NE Department of Recreation
- 310 MacMillon Drive, NE, Office of Communications
- 2200 Adams Place
- 5001 Shepherd Parkway, SW, Impound Lot
- One Judiciary Square
- 300 Indiana Avenue
- 3320 Idaho Avenue
- Reeves Center
Schedule:
| Design |
Spring 2006 - Fall 2006 |
| Construction |
Fall 2008 - Summer 2009 |
| Project Completion |
Fall 2009 |
Budget
$630,000
_________________________________________________
Project: ADA Compliance Design at 611 N Street and 801 E Street
Description:
This project will integrate ADA design into the facilities at 611 N Street and 801 E Street to make them fully compliant with ADA requirements.
Schedule:
| Design |
Summer 2007 - Winter 2007 |
| Construction |
Summer 2008 - Winter 2008  |
| Project Completion |
Winter 2008 |
Budget
$250,000
Project Manager
_________________________________________________
Project: Community of Hope Shelter
Description:
This project includes the ADA Compliance of lifts, toilets, doors, and kitchens. This work is fully incorporated in the Community of Hope Shelter Renovation. Full scope of COH to be performed during Phase II.
Schedule:
| Design |
Spring 2009 - Fall 2009 |
| Construction |
Winter 2009 - Winter 2010 |
| Project Completion |
Winter 2010 |
Budget
$600,000
Project Manager
_________________________________________________
Project: Federal City Shelter
Description:
This project includes the ADA Compliance of lifts, toilets, doors, and kitchens. Only minor work remains to be performed at Federal City, but this work will be performed during Phase II.
Schedule:
| Design |
Spring 2010 |
| Construction |
Summer 2010 - Summer 2011 |
| Project Completion |
Summer 2011 |
Budget
$300,000
Project Manager
_________________________________________________
Project: MPD- 2nd District Police Station; 6th District Police Station; and 6th District Police Youth and Family: Americans with Disabilities Act Compliance
Description:
This project includes the ADA Compliance of lifts, toilets, doors, and accessible routes at each of these sites, to further ADA access to public facilities. Only minor work remains to be performed at Federal City, but this work will be performed during Phase II.
Schedule:
| Design |
Fall 2009 |
| Construction |
Spring 2010 - Fall 2010 |
| Project Completion |
Fall 2010 |
Budget
2nd District $250,000
6th District $250,000
Youth & Family $250,000
Consultants/Contractors
A/E: TBD
GC: TBD
Project Manager
_________________________________________________
Project: DC General Hospital Ambulatory Care Center and Judiciary Square
Description:
This project includes the ADA Compliance of toilets, doors, and accessible routes at each of these sites, to further ADA access to public facilities.
Schedule:
| Design |
Fall 2009 |
| Construction |
Spring 2010 - Fall 2010 |
| Project Completion |
Fall 2010 |
Budget
DC General Hospital ACC Building $250,000
Judiciary Square $245,000
Consultants/Contractors
A/E: TBD
GC: TBD
Project Manager
|